Supply & Install Foundations & Towers for 500 kV OHTL Tanjung Jati B - TX, Ungaran - Pedan, Central Java
CURRENT PROJECT
Supply & Install Foundations & Towers for 500 kV OHTL Tanjung Jati B - TX, Ungaran - Pedan, Central Java

Supply & Install Foundations & Towers for 500 kV OHTL Tanjung Jati B - TX, Ungaran - Pedan, Central Java



• Owner : PT. PLN (Persero) UIP VII

• Source of Fund : APLN

• Design, supply, & construction of
500 kV double circuit overhead T/L, Quadruple Zebra.

• Foundation and Tower for Transmission Line,
83 towers, 36 kmr length from Tanjung Jati B to TX (T.12 - Ungaran – Pedan), including Stringing.